A renovation handover checklist in Greece helps you check five things before you pay the final bill: visible defects in the finishes, every fitting and appliance working, certificates from the electrician and other specialists, invoices and warranties, and a written list of snags with agreed repair dates. Walk through the apartment room by room, and pay the last instalment only once the snags are fixed.

Key takeaways

  • Inspect before the final payment. Once you accept the work, claims for obvious defects become harder.
  • Test every tap, drain, socket, door, shutter and appliance, not just how rooms look.
  • If the electrics were replaced or changed, ask for the electrician’s installer declaration (ΥΔΕ).
  • Collect invoices, manuals and warranties before the contractor leaves.
  • Put the snagging list in writing, with photos and a completion date for each item.

Why does the handover matter before the final payment?

When you still owe money on a job, contractors usually come back fast to fix small problems like a cracked tile or a door that sticks. Once they’ve been paid and moved on to their next project, the same small repair can take weeks to arrange.

There’s also a legal reason. A renovation is usually a contract for work under the Greek Civil Code. According to Article 692, once you’ve approved the finished work, the contractor is no longer responsible for any defects, unless they couldn’t have been spotted during a normal inspection at handover, or were deliberately hidden. For minor defects, Article 688 gives you the right to ask for them to be corrected within a reasonable time, as long as this is not disproportionately costly, or to ask for a proportionate reduction in the price.

This guide is about renovating apartments that are already built. If you’re taking over a newly built home from a developer, the paperwork and time limits are different, and our guide to taking over a new-build apartment in Athens covers that.

The renovation handover checklist for Greece: visible defects and finishes

Walk around the apartment during the day, then again with all the lights on, because low-angle light makes uneven plaster and paint stand out. Go through each room and check:

  • Walls and ceilings: patchy paint, visible filler, hairline cracks along new partitions, marks around sockets.
  • Tiles and grout: chipped tiles, uneven joints, missing grout and tiles that sound hollow when tapped.
  • Silicone: neat, continuous beads around baths, shower trays, basins and worktops, with no gaps.
  • Floors: scratches, gaps between boards, lifted edges at thresholds and loose skirting.
  • Joinery: aligned kitchen doors, smooth drawers, internal doors that close without catching.

Check that everything matches the agreed quote and drawings. If the quote named a type of tile, a number of sockets or a particular door handle, make sure that’s exactly what was fitted.

Fittings and equipment: test everything that runs, drains or opens

A renovation might look great and still have a basin that drains slowly. In the renovation final inspection, test each thing separately to make sure it works.

Water and drainage. Run every tap, hot and cold. Fill and empty each basin, sink, shower tray and bath, and watch for slow drainage. Flush every toilet several times, then look under kitchen and bathroom units with a torch for drips. Check that the water shut-off valve turns.

Electrics. Try every switch, light and socket, including on the balcony. Ask the electrician to confirm that each circuit in the panel is labelled, and press the test button on the residual current device.

Heating, cooling and hot water. Check the water heater delivers hot water to the furthest tap. Run each air conditioning unit in cooling and heating mode and check that condensate drains away properly. If radiators were touched, run the heating and check new joints for leaks.

Windows, doors and shutters. Open, close and lock every window and balcony door, roll each shutter fully up and down, and check you have every key.

Appliances. Run the oven, hob, extractor, dishwasher and washing machine briefly while the installer is there, and ask how each one works.

“Never let the final inspection be the first time you see the work. I check against the quote throughout the job, so the handover is about the last details, not about discovering that the wrong tiles went in three weeks ago. And I always test with water: fill every basin, run every shower, then look underneath with a torch.”
– Yanis Zisis, Founder of Home Watch Athens

Which documents should you receive at handover?

It’s far simpler to collect the paperwork while the contractor is still on the job. Before you make the last payment, ask for:

  • Invoices and receipts for the works and any materials you paid for directly, matching the agreed quote.
  • The electrical paperwork: the installer’s declaration (ΥΔΕ) if the electrics were replaced or modified, plus an updated panel diagram.
  • Engineer’s documents if the works had a small-scale works approval (EEDMK) or any other permission.
  • Manuals and warranty cards for every appliance, the water heater, air conditioning units, boiler and any new windows.
  • A list of suppliers and products, including tile names, paint colours and batch numbers.
  • Photos of hidden work, such as pipework and cabling before the walls were closed, especially if you moved a kitchen or bathroom.

Keep digital copies in one place.

Warranties: what to collect and who to call

There are usually two types of warranty. One is from the manufacturer and covers equipment such as the water heater, air conditioning, appliances and windows. Some manufacturers require the product to be registered or fitted by an authorised installer, so ask your contractor to confirm this and hand over the paperwork.

The second is the contractor’s own commitment on workmanship. Agree in writing what they’ll come back to fix, such as a leaking joint, and for how long, with the name of a specific person to contact rather than a general office number.

The role of specialist certification

You can’t always tell how good a job is just by looking at it. Wiring, gas pipes and structural changes are hidden behind walls and under floors, so their safety depends on qualified people signing them off. If the flat is an older one, our guide to renovating an old apartment in Athens covers what tends to be hiding behind the walls.

For electrics, the Hellenic Electricity Distribution Network Operator explains on its electrical safety page that every new electrical installation, and every existing one that is modified, needs an inspection. The electrician who inspects it records the findings in the installer’s declaration, the ΥΔΕ, which the owner or user also signs. It can be co-signed and certified online through the gov.gr installer declaration service.

If the works had a small-scale works approval (EEDMK), the engineer may file a declaration in the electronic permits system when the works finish before the approval expires, so ask whether this applies. If a gas boiler or gas pipes were relocated, get the paperwork from the certified gas installer. If you’re unsure about waterproofing or structural changes, such as removing an internal wall, an independent engineer’s opinion is worth more than a contractor’s reassurance.

How should the agreed snagging process work?

Snagging is the list of things that aren’t quite right or still need finishing, and the process matters as much as the list:

  1. One written list, numbered. Each item has a room, a short description and a photo.
  2. Agreed responsibility and dates. For each item, write who fixes it and by when. Ask the contractor to confirm the list in writing.
  3. A retention. A final instalment held back until the snags are fixed, ideally agreed in the original contract along with how delays and extra costs are handled.
  4. A second inspection. Check each repair, or have someone you trust check it, before ticking it off.
  5. Final payment and sign-off. Pay once the list is closed, and note any item you have agreed to leave open.

If you live abroad, someone on the ground needs to attend both inspections and follow up afterwards.

After the handover: the first months

A newly renovated home is still settling. The plaster keeps drying, silicone can shrink, and a slow leak under a new basin might not show for weeks. If the apartment sits empty while you’re abroad, nobody sees these early signs. A check a few weeks after handover, then regular monthly property checks, catch small issues while the contractor is still willing and able to fix them.

How Home Watch Athens can help

We carry out renovations in Athens, and we also oversee renovations run by your own contractors. Through our renovation oversight service, Yanis checks the work against the quote as it’s being done, prepares the snagging list at handover, follows up on repairs and sends you photo updates on WhatsApp. Afterwards, the monthly Home Watch visit keeps your home checked while you’re away. We’re a trusted person on the ground, here to guide you, not to profit from you. Apply for Membership and Yanis will reply within 24 hours.

Frequently asked questions

Should I pay the contractor in full before the snagging list is finished?

It is better not to. Agree a final instalment released only once every item on the written snagging list is fixed and checked. Contractors usually return quickly while money is still owed. If the contract had no retention, confirm in writing that the last payment follows the second inspection.

What is a ΥΔΕ and do I need one after a renovation?

The ΥΔΕ is the installer’s declaration in which a qualified electrician records the results of inspecting an electrical installation. HEDNO says every new or modified installation needs an inspection, so if your renovation replaced or changed the wiring, the panel or circuits, ask for one. It can be co-signed and certified online through gov.gr.

Can someone else do the final inspection if I live abroad?

Yes. A trusted representative can walk the apartment with the contractor, test fittings, photograph defects and agree the snagging list on your behalf. Decide in advance who has the authority to approve the work and release payments, and keep that in writing so the contractor knows who to deal with.

What happens if I find a defect after the handover?

Contact the contractor straight away in writing, with photos and a clear description. Approving the work can limit claims for defects a normal inspection would have found, but hidden defects are treated differently. For anything significant, such as water coming through a wall, get an independent engineer’s view and speak to a lawyer about your contract.

This guide is general information, not legal or technical advice. Your rights depend on your contract and the works carried out. For your own situation, you can always consult a lawyer or a licensed engineer.