Most renovation delays in Greece, and the extra costs that follow, are built in from the start. A scope that isn’t clearly defined, finishes that haven’t been chosen, late orders and changes agreed over the phone all add weeks and money. Get the scope in writing, make decisions early, price every change before it’s made and keep a single written record of all approvals.
Key takeaways
- A written, itemised scope is the single best protection against extra costs.
- Choose tiles, sanitaryware, kitchen and fittings before work starts, not while the trades wait.
- Every change should have a written price and a time impact before it goes ahead.
- Keep one approval record that you, the contractor and anyone overseeing the job can see.
- Disputes over money or defects are a matter for a lawyer; good records make that conversation shorter.
Why do renovation delays in Greece happen so often?
Owners abroad often point to slow trades as the main reason for delays. From what we’ve seen, the real issue is usually simpler: the project wasn’t clearly defined from the start. A quote might just say “bathroom renovation” without spelling out what’s being removed, what’s being replaced and to what standard. Nobody has chosen the tiles, or the kitchen hasn’t been ordered. So the plumber finishes his first fix and has nothing to do for three weeks.
Other common causes:
- Hidden conditions. Old galvanised pipes behind tiles, wiring that doesn’t meet current standards or uneven floors only show up once walls and floors are opened.
- Supplier lead times. Many tiles, fittings and kitchens are made to order or imported, and stock can’t always be confirmed until you order.
- The calendar. Many suppliers and workshops slow down or close for part of August, and Easter and Christmas also cost time.
- Building access. Your building’s rules, the diaxeiristis and the neighbours can all affect when noisy work, deliveries and rubbish removal can happen.
- Paperwork. If the works need a permit or approval, that has to be in place first.
None of these is unusual on its own. What makes them costly is finding them out halfway through. Our apartment renovation timeline guide shows how the stages fit together.
What should be agreed in writing before work starts?
Before you sign anything, get a scope document that a stranger could price: rooms, quantities and specifications, not just headings. If you’re getting several quotes, a detailed scope is the best way to compare them fairly.
At a minimum, the written agreement should cover:
| Item | What to pin down |
|---|---|
| Scope | Every task, room by room, with quantities (m², number of points, units) |
| Specification | Brands or standards for tiles, sanitaryware, taps, flooring, paint, electrics |
| Who supplies what | Which materials the contractor buys and which you buy or choose |
| Exclusions | What is not included, such as furniture, appliances, or repairs found behind walls |
| Programme | Start date, the order of trades and a realistic finish date |
| Payments | Staged payments linked to completed stages, not to dates |
| Changes | How changes are requested, priced and approved |
| Handover | Cleaning, a snagging list and who fixes what afterwards |
Check whether prices include 24% Greek Tax. As a guide, renovation works start from €600/m² (excluding 24% Greek Tax). Contractor quotes in Greece often end up higher than first quoted, usually because the original scope left things out. If you’re paying from another country, our guide to paying contractors in Greece from abroad explains how to stage payments sensibly.
Check the paperwork side early
In Greece, some works need a permit or a small-scale works approval before they start. That approval, called Έγκριση Εργασιών Δόμησης Μικρής Κλίμακας, is submitted online by an engineer through the Technical Chamber of Greece’s e-permits system. The categories of works are set out on the official procedure page for small-scale works approval. If you’re wondering whether you need a permit to renovate an apartment in Greece, our guide goes into more detail.
The works may also need registering with e-EFKA, the social insurance body, before they begin, with the owner treated as the responsible employer for insurance contributions. It depends on the type of works, so ask your engineer or contractor at the quote stage.
How do missing decisions turn into extra costs?
Every unmade decision is a gap in the programme. When the tiler shows up and the tiles aren’t chosen, one of three things happens: he leaves and comes back another time (delay), he waits (cost) or someone chooses for you on the spot (regret).
The solution is a decision schedule. Before work starts, list every decision the project depends on and the deadline for each one, so everything can be ordered in time:
- Floor and wall tiles, including grout colour
- Sanitaryware, taps, shower screens
- Kitchen units, worktops and appliances
- Doors, handles and interior joinery
- Lighting positions, sockets and switches
- Paint colours
Make the decisions that affect first fix first. Socket and lighting positions need to be settled before the electrician closes the walls. Moving a socket later means cutting into the wall, plastering and repainting.
How should renovation change orders be handled?
Changes are normal: you might decide you want a wall moved, or the contractor might find rotten pipework. The problem is a change agreed in the hallway with no price attached.
A basic rule for renovation change orders: nothing changes until it is in writing. For every change that comes up, ask for:
- A short description of what changes and why.
- The extra cost, or the saving, with 24% Greek Tax shown.
- The effect on the finish date.
- Your written approval before work on it starts.
Number them: Change 1, Change 2, Change 3. When the job is finished, the final bill should be the original price plus or minus these changes. Anything not on the list is open to question.
Watch for “while we’re here” suggestions. Some are genuinely helpful, but they add up quickly, and each one should go through the same written process.
How do you keep an approval record from abroad?
From London, Dubai or Sydney, most decisions are made on WhatsApp. That works if you have a clear record of what was agreed, but voice notes and calls don’t count as a record.
A workable system:
- One thread for decisions. Keep a separate group or document for approvals only, apart from day-to-day chat.
- Confirm calls in writing. After any call, send a one-line summary: “Agreed: Change 4, extra €X plus 24% Greek Tax, adds 3 days.”
- Photograph before closing up. Ask for photos of pipework and wiring before walls and floors are closed.
- Date your photos. Progress photos with dates help settle questions about what was done and when.
- Keep the documents together. Quote, scope, changes, invoices and receipts in one folder.
If money or defects become a dispute, it’s time to talk to a lawyer. A clean record makes any disagreement much easier to resolve.
Deliveries, access and the building
Deliveries often cost days in Athens. Many apartment buildings have small lifts, narrow stairwells and limited street access. So, before you order something, make sure to check:
- whether large items (kitchen units, shower trays, worktops) fit in the lift or need carrying by stairs;
- who will be on site to receive and check each delivery for damage;
- where materials will be stored without blocking common areas;
- how rubbish will be removed, and whether a skip is allowed on the street.
Tell the diaxeiristis and your neighbours the planned dates ahead of time; it avoids a great deal of friction. If you are planning wider works, our guide to renovating an old apartment in Athens covers what to check first.
“Before a single tile comes off, sit down with your contractor and agree three things: exactly what is included, which decisions you need to make and by when, and how any change will be priced and approved. Most of the renovations I see run late or over budget fail on one of those three, not on workmanship. And if you are abroad, make sure someone you trust is seeing the work with their own eyes, not just in photos the contractor chooses to send.”
– Yanis Zisis, Founder of Home Watch Athens
How Home Watch Athens can help
We help owners abroad agree the right details before work begins and track them throughout. With our renovation oversight service in Athens, Yanis can walk through the home with your contractor, review quotes line by line, accept deliveries, check work against what was agreed and maintain a clear photographic record via WhatsApp. If you prefer, we can also carry out the work ourselves through our home renovation services in Athens. Apply for Membership and Yanis will reply within 24 hours.
Frequently asked questions
Is it normal for a renovation in Greece to cost more than the quote?
It is common, mostly because first quotes are often based on a short description rather than a detailed scope. Hidden conditions, such as old pipes or wiring found once walls are opened, and changes requested during the works also add cost. A detailed scope, clear exclusions and a written process for changes keep the final bill close to the original price.
Who pays when hidden problems are found behind walls?
Usually the owner, unless the contract says otherwise, because hidden conditions are rarely included in a fixed price. That is why your agreement should say how unforeseen work is priced and approved. Ask the contractor to stop, show you photos, and send a written price and time estimate before going ahead. Anything significant should go on your numbered change list.
Should I pay a renovation contractor in Greece in advance?
A deposit at the start is normal, but larger payments should be linked to completed stages, such as demolition finished or first fix done, rather than to dates. That keeps the payments in step with progress. Keep each invoice and payment confirmation with your quote and change records so the final account is easy to check.
What is a change order in a renovation?
A change order is a written record of any change to the agreed works, whether you asked for it or the contractor found it was needed. It should describe the change, its cost or saving, its effect on the finish date and show your approval. Numbering each change makes the final account straightforward to check against the original quote.
How can I keep a renovation on schedule if I live abroad?
Make all your design and product decisions before work starts, order long-lead items early and agree a clear order of trades. Confirm every decision in writing, ask for dated progress photos and make sure someone you trust visits the site regularly to check the work against what was agreed, rather than relying only on the contractor’s updates.
This guide is general information, not legal advice. For your own situation, including any dispute with a contractor, you can always consult a lawyer.