A realistic apartment renovation timeline in Athens is around four to six months from the first site visit to handover, for a typical two-bedroom flat that needs a full renovation. The building work itself usually takes eight to fourteen weeks. What really sets the pace is the time it takes to design everything, get approvals and order materials before the works begin.

Key takeaways

  • A full renovation of a 70–90 m² apartment usually runs four to six months, start to finish.
  • Only about half of that is building work; the rest is briefing, design, approvals and procurement.
  • Made-to-measure kitchens, windows and some imported tiles often have the longest lead times, so order them early.
  • A small-scale works approval (EEDMK) is issued electronically once the engineer submits it, but preparing the file takes time.
  • Plan one to two weeks at the end for snagging, certificates and a final clean.

What does a realistic apartment renovation timeline in Athens look like?

The building work is part of a bigger process. In Athens, renovating an apartment involves five stages: briefing, design and approvals, procurement of materials, the works, and handover. Each step relies on the one that comes before it, and some overlap.

The table below lists a standard plan for fixing up an old two-bedroom apartment from the 1970s or 1980s that’s about 80 m², in a polykatoikia. This includes putting in a new kitchen, one or two new bathrooms, updating the electrical and plumbing systems, installing new floors, and redecorating everything.

Stage Typical duration What it depends on
Briefing and site visit 1–3 weeks Access to the home, contractors available to visit and quote
Design and approvals 3–8 weeks Layout decisions, material choices, engineer’s file, any co-owner consent
Procurement 2–8 weeks (overlaps with design and early works) Final measurements, supplier lead times, stock
Works 8–14 weeks Scope, drying times, trades turning up in sequence
Snagging and handover 1–2 weeks Defects list, certificates, final clean

All in all, you’re looking at around four to six months. Smaller jobs move faster. Redoing one bathroom usually takes three to five weeks of works, and a paint, flooring and lighting refresh with no layout changes can often be done in four to six weeks in total.

Stage 1: Briefing and the site visit (weeks 1–3)

It all begins with a walk-through of the apartment. This is where the scope is written down: which walls stay, which rooms are stripped back, whether the electrics and plumbing are replaced or only repaired, and the level of finish you want. In an older Athens apartment, this is also the time to spot issues that could throw off the schedule, such as old galvanised pipes or damp in the external walls.

To price the work properly, contractors need to see the home first. Having two or three of them visit and getting their written quotes back usually takes one to three weeks. If you live abroad, this can be slower still, since someone needs to be there to let the contractors in and explain the brief.

Stage 2: Design and approvals (weeks 3–10)

Once the scope is agreed, the design is finalised: the layout, the kitchen and bathrooms, where the sockets, lights and air conditioning points go, and the main materials. Changes during the works are what stretch a timeline most, so it’s best to settle all this now.

Do you need a permit, and how long does it take?

Many interior renovations don’t need a building permit, but some works do need paperwork. Wider internal rearrangements, such as moving walls, are among the works listed under the small-scale works approval, the EEDMK, and your engineer will confirm which route applies to your plans. Under the Ministry of Environment and Energy decision on small-scale works approval, the engineer submits the application electronically and the approval is issued automatically straight after submission. It is valid for one year.

The approval itself is quick, but preparing for it is a different story. The engineer has to measure the apartment, draw the existing and proposed layouts and collect the supporting documents, which usually takes two to four weeks. If the works affect common parts of the building, like the facade or the shared structure, co-owner consent may also be needed, which can mean waiting for a building meeting. Our guide to renovation permits in Greece breaks down what’s needed for different types of work.

Stage 3: Procurement and lead times (overlapping weeks 4–12)

Renovations in Athens often lose time at the procurement stage without anyone noticing. Some items are in stock with suppliers around Attica and can arrive within days. Others are made to order:

  • Kitchens are built after the final measurement, which is taken once walls are plastered. Factory lead times of four to eight weeks are common.
  • Aluminium windows and balcony doors are made to measure and often take three to six weeks.
  • Imported tiles, sanitaryware and some taps can take two to six weeks if they are not held in stock locally.

It’s best to place these orders early, during the design stage or the first weeks of works. If you wait, you’ll end up with a bathroom that’s all plumbed in but has no tiles, and nothing gets done for weeks.

Stage 4: The works, in the order they happen (weeks 8–22)

The works follow a fixed order, since each trade relies on the one before it. This order of works in a renovation is the same in almost every Athens apartment. For a full renovation, it usually goes like this:

  1. Strip-out and demolition (1–2 weeks): removing old kitchens, bathrooms, flooring and any walls coming down, plus clearing the rubble. Furniture has to be out before this stage: see where to put your furniture during a renovation in Athens.
  2. First fix plumbing and electrics (2–3 weeks): new pipework, drainage, cabling and the new electrical panel, all before walls are closed.
  3. Walls, screeds and waterproofing (1–3 weeks): plastering, levelling floors and waterproofing wet areas. Screeds and waterproofing need drying time, which is longer in a damp winter.
  4. Tiling and flooring (2–3 weeks): bathrooms, kitchen splashbacks and floors throughout.
  5. Kitchen, doors and joinery (1–2 weeks): fitting the made-to-measure items ordered earlier.
  6. Painting (1–2 weeks): usually two coats, with filling and sanding between.
  7. Second fix and fittings (about 1 week): sockets, lights, taps, sanitaryware, air conditioning units.

Two factors catch many owners off guard. First, most apartment buildings have rules about noisy work, so it’s wise to give the building manager and neighbours notice before demolition begins and to agree working hours beforehand. Second, many suppliers and tradespeople slow down or close around the 15 August holiday, so a summer start needs planning around it. Our guide to the best time to renovate in Athens explains how to plan around it.

“The single biggest thing an owner can do to keep a renovation on time is finish every decision before demolition starts. Choose the tiles, the kitchen and the fittings, order anything made to measure, and only then let the first wall come down. Most of the delays I see on Athens projects are not the builders being slow, they are the builders waiting for a decision or a delivery.”
– Yanis Zisis, Founder of Home Watch Athens

Stage 5: Snagging and handover (final 1–2 weeks)

When the builders say they are finished, the project is not quite done. The home still needs a thorough walk-through to list anything that isn’t right, from a chipped tile to a door that won’t shut properly. The contractor then comes back to fix those items, which usually takes a few days to a week.

Handover is also when the paperwork comes together. If the electrics were replaced or modified, an inspection is required, and the licensed electrician records the results in the Υπεύθυνη Δήλωση Εγκαταστάτη (ΥΔΕ), the installer’s declaration described on the HEDNO electrical safety page. Keep a copy with the warranties, invoices and the engineer’s documents. After a final clean, the apartment is ready to use.

Why do renovation timelines in Greece slip?

Timelines usually slip because the scope changes once works have started, materials don’t turn up on time, or hidden problems are found behind walls and floors. Contractors also often juggle several jobs at once. Our guide to renovation delays and extra costs looks at this in more detail.

If you’re working towards a fixed date, such as a summer arrival, add a margin of three to four weeks to the schedule above.

How Home Watch Athens can help

We carry out kitchen, bathroom and full-home renovations in Athens for owners who live abroad, and we also oversee renovations run by your own contractors. With our renovation oversight service, Yanis walks the home with each contractor, visits as the works progress, sends photo updates on WhatsApp and prepares the snagging list at handover. If you’d rather have one team handle everything, see our home renovation services in Athens. Either way, you have a trusted person on the ground who is there to guide you, not to profit from you. Apply for Membership and Yanis will reply within 24 hours.

Frequently asked questions

How long does it take to renovate an apartment in Greece?

For a full renovation of a typical two-bedroom apartment, allow four to six months from the first site visit to handover. The building works usually take eight to fourteen weeks of that. A single bathroom or a cosmetic refresh with no layout changes is much quicker, often four to six weeks in total, as long as materials are chosen and ordered before work starts.

How long does an EEDMK approval take?

The small-scale works approval is issued automatically once the engineer submits the application electronically, so the approval itself is immediate. The time goes into preparation: measuring the apartment, drawing the layouts and gathering documents, which often takes two to four weeks. If common parts of the building are affected, co-owner consent can add further time.

Which renovation stages in Athens take the longest?

The works stage is the longest single block, but procurement and design often decide the finish date. Made-to-measure kitchens, aluminium windows and imported tiles can take several weeks to arrive. If they are ordered late, tradespeople wait on site with nothing to fit, and the whole schedule moves back.

When should I start planning a renovation for a summer arrival?

Start planning around six months before you want to use the home, and earlier if the works involve layout changes or new windows. That leaves time for quotes, design, approvals and ordering, plus a margin of a few weeks. Remember that many suppliers slow down around the 15 August holiday, so aim to finish before then.

This guide is general information, not legal or technical advice. Permit requirements depend on the exact works and the building. For your own situation, you can always consult a licensed engineer or a lawyer.

Last updated: November 2026