Merging two apartments in Greece is a two-part process. First, opening a doorway between two flats you own is a construction job, and it needs an approval that an engineer files before the work starts. This is a separate step from making the two flats one property in the eyes of the law. That normally takes a notarial deed, registered at the Cadastre once the building work is done. You can do the first without the second, and your choice decides what shows up on your tax record and utility accounts.

Key takeaways

  • The permit rules now sit in Law 5306/2026, the Code of Spatial and Urban Planning, which lists the functional merging of spaces among the works that need a small-scale works approval.
  • The 67% consent in the Code is counted among the co-owners of the adjoining flats being joined. Work that touches the load-bearing structure is a separate matter, and there the consent of the building’s co-owners comes in.
  • Until a deed says otherwise, you still own two properties: two lines on the E9, two shares in the plot, two sets of common charges and two meters.

What does the law call it when you join two apartments in Greece?

The rules for planning and building that were once scattered across many laws have been in one place since June 2026, in a new Code ratified by Law 5306/2026. If you’re a property owner, you might remember the permit routes from Law 4495/2017. Those rules are now covered in Articles 315 and 316. We have a guide that breaks down the three approval routes for renovation work, and it explains what sets them apart.

Article 315 outlines the works that require a small-scale works approval, and two entries stand out. Firstly, it covers internal rearrangements, but only if the load-bearing structure remains untouched. Secondly, it lists the functional merging of spaces, which is regulated in Article 220, paragraph 5. This paragraph allows independent properties in the same building to be functionally joined, provided that their owners agree with an enhanced majority of at least 67% and the building’s structural adequacy is secured after the changes. Article 327 lists the necessary documents and specifies whose consent is required: 67% of the co-owners of the adjoining independent properties, in this case the apartments being merged. This majority applies to the functional joining and related rearrangements, not to work on the building’s frame, which has its own rule further down.

When the statutory budget for a project, counted for each property, goes over the limit stated in Article 315, it needs a full building permit. This means the project has to meet more requirements.

Side by side or one above the other?

If you’re looking at two apartments on the same floor, they’re separated by a wall. In a polykatoikia with a concrete frame, the space between the columns is often filled with bricks, and a doorway cut through this brick section leaves the main frame intact. Sometimes, though, the wall between the flats turns out to be a concrete wall section.

When you have two flats on different floors, they’re separated by a slab. This slab is part of the building’s load-bearing structure, so cutting into it to add an internal staircase is never a simple rearrangement. Because of this, if you want to merge two flats vertically, the work falls under the Code’s rule for the load-bearing structure, and that means a structural adequacy study behind it.

The wall between: who checks it and who signs?

A civil engineer will look at the wall and compare it to the building’s approved drawings. If the drawings are missing or unclear, they will open small test points to check. We wrote about what to check before taking out a wall inside one flat, and that post covers the details of this inspection.

The engineer then files the approval online. When properties in the same building are being merged, Article 327 of the Code says what needs to be included in the file:

  • an application from each owner of the spaces being joined
  • the engineer’s technical report, which describes the works and states that structural adequacy is not affected
  • copies of the building permits
  • the consent, by a 67% majority, of the co-owners of the adjoining independent properties
  • architectural drawings (plan and section), with the fire-protection study amended for the joined space
  • a copy of the topographic diagram

When the documents are submitted under Article 323, the approval is given automatically and work can start as soon as the number is posted. The engineer is responsible for the filing.

If the merger needs work on the load-bearing parts, Article 220 says it’s allowed if the people who co-own the building agree. There’s an exception: it can still happen without their consent, even if the building’s rules say no, as long as a structural adequacy study shows the building is still sound.

What does the building have to agree to?

When you’re dealing with a doorway through a wall that’s not part of the main frame, the Code’s 67% concerns the co-owners of the two flats on either side of the wall. It’s not about a vote of the entire building. However, if the work starts to involve common parts like the load-bearing structure or the facades, then the building comes in. At this point, the file needs the consent of the co-owners, and it can be proven by any lawful means. The Code mentions two examples specifically: declarations with certified signatures, and the minutes of a general assembly.

The building’s own regulation, known as the kanonismos, might have some extra rules for altering flats or for the front doors on each landing. We have a guide to neighbours, lifts and access during works in a polykatoikia that helps with the practical side.

When you do a functional merger, it doesn’t affect your shares. Each apartment still has its own share of the plot, in thousandths, and things like common charges, the lift and heating are still split between the two units based on the building’s tables.

Legal merger, or two properties used as one?

When the works are done, you’ll have one home and two properties on paper. You can choose to stop at this point if you want. The usual route for the next step is a notarial deed that amends the horizontal-ownership description so that the two units are described as one. This deed is then registered with the Cadastral Office. To do this, the notary who prepared the deed or one of the parties to it submits it through the Cadastre’s online service for registering a notarial deed.

E9 and ENFIA

AADE works out ENFIA from the property you hold on 1 January every year, based on the information in your E9. As long as the flats are still two separate properties, the E9 will have two entries. Once a deed changes that, a declaration of change is filed in the E9 application on myAADE, and then the next ENFIA will be based on the updated information.

Electricity and water

Each apartment has its own electricity supply and its own water meter, and things keep running as usual until you ask for a change. The operator of the electricity network, HEDNO, has a specific request for unifying two power supplies. They need a few things from you: a declaration of consent from each owner, a copy of the title deed, a new certificate from a licensed electrician that describes the changes made to the installation, and a document from the municipality that shows the updated square metres of the supply that stays active.

Kitchens, bathrooms and the second front door

If you have two flats, you get two kitchens and two separate entrances. Taking out one kitchen is plumbing and electrical work inside your own walls. The water pipes that supply the kitchen are capped and the drain is sealed off where it connects to the vertical stack that runs up the building, and that stack stays right where it is.

The second front door is different because it leads out to a shared landing. If you were to wall it up, it would alter what the neighbours see in a common area, so it belongs in the discussion with the building. The amended fire-protection study treats the joined flat as a single space. By keeping both doors, you’re leaving the option open to separate the flats again in the future.

“When I visit a flat that was joined years ago, the first thing I ask for is the approved drawing of the opening. If nobody can find it, the simplest plumbing job turns into detective work. Keep one folder with the approval, the engineer’s drawings and the consents, and keep a copy outside the flat.”

Yanis Zisis, Founder, Home Watch Athens

Can you reverse it later?

Yes. If the flats were never officially merged by deed, the title already lists them as two separate units, and Article 327 says the same documents apply if you separate them again after a functional merger. But if they were legally merged, then separating them is a division of a horizontal property, which is a different process that Article 315 lists with its own documents. We’ve got a post that goes through the steps of dividing one flat into two homes.

Managing a merger from abroad

Most of this can be handled from a distance, without you being in Athens. The engineer submits the file online and the approval is issued electronically. But one thing requires someone to be physically present: seeing what was actually built. That’s where our renovation oversight service in Athens comes in. It’s quoted separately from membership, and Yanis follows the works at the site, takes photos and sends updates. After the renovation is done, the monthly home visit continues. If you have two apartments in Athens and want them looked after as one home, Apply for Membership.

Frequently asked questions

Do I need a permit to open a door between two flats I own?

Yes. Under the Code ratified by Law 5306/2026, the functional merging of spaces is on the list of works that need a small-scale works approval. An engineer files it electronically with a technical report, drawings, copies of the building permits and the owners’ consent.

Do the other owners in the building have to agree?

Not for the joining itself. The 67% majority in the Code is counted among the co-owners of the adjoining flats being joined, and the engineer’s report states that structural adequacy is not affected. Work on the load-bearing structure is different: it needs the consent of the building’s co-owners, shown through certified declarations or assembly minutes, or a structural adequacy study showing the building remains sound.

What happens to ENFIA after a merger?

ENFIA is calculated from the property you hold on 1 January and the details in your E9. While the flats are two properties, they appear as two entries. After a deed joins them, a declaration of change is filed in the E9 application on myAADE, and the following ENFIA is based on the updated record.

Can I keep both electricity meters?

Yes, both supplies continue until you ask HEDNO to change them. To unify them, a licensed electrician alters the internal installation and issues a new certificate, and the request goes to HEDNO with owner consent declarations, a copy of the title deed and a municipal document showing the updated square metres of the supply that remains.