Last reviewed: November 2026
Yes, you can split an apartment into two in Greece, but a few things need to fall into place. First, the construction work needs an approval that an engineer files, under the permit rules of the Spatial Planning and Urban Planning Code, which is Law 5306/2026. Then, the deed of horizontal ownership needs to be updated by a notary, so that it shows two separate properties on paper. The building itself also has to allow for this division, either through its own rules or with the agreement of the other owners.
Key takeaways
- Dividing a flat (katatmisi diamerismatos) is building work with its own approval route.
- Each new flat needs its own entrance from the common landing, direct daylight and ventilation in its main rooms, a kitchen and a bathroom.
- The second kitchen and bathroom must reach the building’s shared waste stack by gravity. This is the usual reason a split fails.
- The original flat’s share in the plot is divided between the two new flats, and the common charges and lift shares follow.
- Afterwards come the notarial deed, the Cadastre, the E9 and the building identity record.
Why do families split one large flat?
A common situation is a family one. Usually, the parents own a big apartment from the 1960s or 1970s, sometimes the whole floor. They have two children who live in other countries. So they divide the apartment into two smaller ones, each with its own entrance and deed, so each child gets their own place in Athens, rather than half of one.
If you want to combine two neighbouring flats into one, it’s the opposite case, but it works in a similar way. We have a guide to joining two flats into a single home.
Is it allowed? The approval under Law 5306/2026
The rules for building permits have had a new home since June 2026. They are part of the Spatial Planning and Urban Planning Code, which was ratified by Law 5306/2026. This law was published in the Government Gazette A 88 on 8 June 2026, and it came into effect on publication. The Code took over the permit rules from an older law, Law 4495/2017, which is why some official websites still show the old article numbers.
Article 315 explains what kind of administrative act you need for different types of construction work. In its second paragraph, the separation of horizontal properties appears on the list of works that need a small-scale works approval, and this applies regardless of the budget. Article 327 outlines the necessary paperwork and Article 329 specifies the duration of the approval.
An engineer sends in the application online through the e-Adeies system run by the Technical Chamber, and the approval is issued when it is submitted. For a split, the file has:
- a copy of the topographic diagram of the plot,
- the engineer’s technical report describing the works, with a declaration that the load-bearing structure is not affected,
- a floor plan at 1:100 or 1:50 showing the two new flats,
- a notarial declaration of parking spaces under Law 1221/1981, where the extra home creates a parking obligation,
- any building studies that change, and proof that the existing flat is lawful.
The approval is good for one year from the day it’s issued. This route only suits work that doesn’t touch the main structure. If the plan involves cutting into columns, beams or slabs, then a full building permit is needed. We have a guide that explains which renovation works need a permit in Greece, and it lays out the three routes.
What must each new flat have?
The engineer’s plan has to show two homes that each work independently.
Its own entrance. Every flat should have its own way in. This means each one needs a door that opens onto the shared landing. Some of the bigger, older flats already have two doors. If you add a new door to the landing wall, you’re changing something that’s shared, so the consent of the other owners goes into the file.
Daylight and ventilation. A home’s main spaces, like the living room and bedrooms, should have their own light and ventilation. So, the wall that divides the flat should be placed to follow where the windows are.
Rooms that work as a home. Every flat needs a space to live in, a kitchen to cook in, and a bathroom for itself.
Drainage and the stack: the usual reason a split fails
A second flat means you’ll need a second kitchen and a second bathroom. This also means drainage for both, and they’ll need to connect to the building’s shared vertical waste pipe, the stack. If the new bathroom is far from any stack, the pipe cannot keep sloping downwards so everything flows by gravity, and the plan stops there. We have a guide on what to check before relocating a kitchen or bathroom, which covers falls, ventilation and gas in detail.
Before you finalise any drawings, have the flat checked on site to see where every stack runs and what kind of shape each is in. Also find out if the new connection can be made inside your own apartment. If the connection needs work in the apartment below yours, or if a new pipe has to run down the facade or through a light well, it involves common parts. Any work on common parts requires the consent of the other owners.
Does the building have to agree?
Usually, yes. The deed of horizontal ownership lists all the flats in a building and the share each one holds. To make changes to it, you generally need one of two things: a clause in the regulation that says an owner can split a unit, or the agreement of the other owners. Regulations are different in every building: some let you split units, some don’t, and some limit how many homes can be on each floor.
To get started, you should take a look at the regulation that governs your building. We’ve put together a guide that explains getting a copy of your building’s regulation and reading it. When it comes to works on common parts like the facades or the load-bearing structure of the building, the approval file, separately from the deed, includes a statement from the co-owners saying they agree to the work. This can be shown with signed declarations or with the minutes of a general meeting.
Meters: electricity, water and heating
Electricity. HEDNO handles this as a separation of supplies. The owner applies online and provides some documents. These include a consent declaration from each owner, a copy of the property title, and a new certificate from a licensed electrician for each of the two installations. They also need the connection certificates from the Technical Chamber. After HEDNO gives the new supply a number, they need a document from the municipality that confirms the updated square metres. All the details are on HEDNO’s website, on its page for unifying or separating electricity supplies.
Water. The original apartment has one EYDAP meter. Usually the second apartment gets its own meter and account, which the owner asks EYDAP for. Until that’s done, both places share one account.
Heating. Heating setups differ in each building. Where central heating is used, the radiators usually stay on the same risers, with the flat’s heating share split between the two new flats. But when a flat has its own boiler or heat pump, the second flat typically gets its own heat source.
Shares in the plot, common charges and the lift
Each apartment has a share of the plot it stands on, which is measured in thousandths. If someone divides an apartment into two, the usual approach is to split its thousandths between the two new apartments, commonly based on the floor area of each one. This way, the total for the whole building stays the same.
For each table in the regulation, things like general common charges, the lift, and central heating are usually treated the same way. The new numbers are put in the amending deed, and the building manager needs a copy. This way, when they send out the monthly statement, it will show that there are two apartments.
“Before anyone draws a wall, find the stacks and read the regulation. I have stood in flats where the family had already agreed who gets which half, and the half without a waste pipe could never have had a bathroom. Those two checks tell you whether you have a project.”
Yanis Zisis, Founder, Home Watch Athens
The paperwork afterwards: notary, Cadastre, E9
- Notary. A notary draws up the deed amending the horizontal ownership. It describes the two new flats, their areas and their thousandths.
- Cadastre. The deed is submitted to the Hellenic Cadastre for registration, so that its records show two flats where there was one.
- E9. The owner’s property record at the tax authority is updated: one flat becomes two. AADE’s rule is that the owner files the E9 by 31 January of the year after the change, through the E9 application on the AADE website.
- Building identity. The electronic building identity is completed by an authorised engineer registered with the Technical Chamber, for a building or for a single divided property. After a split, the engineer brings the record into line with the two flats.
How we help members with a split
Splitting a home from afar can be a lengthy process. Our renovation oversight for Athens homes means that Yanis will visit the site, taking photos of each stage of the work, including the pipework before the floors are closed, and sending you a report. As a member, you’ll also get a monthly home visit and photo update. If you own a home in Athens or Attica but live outside of Greece, you can Apply for Membership.
Frequently asked questions
Do I need a permit to split an apartment into two in Greece?
Yes. The separation of horizontal properties is listed in Article 315 of the Spatial Planning and Urban Planning Code (Law 5306/2026) among the works that go through a small-scale works approval, filed electronically by an engineer in the e-Adeies system. If the works affect the load-bearing structure, the project needs a full building permit instead.
Can the other owners stop me dividing my flat?
It depends on the building’s own documents. Where the regulation forbids division or limits the number of homes, the other owners are generally able to hold you to it. Where it lets an owner divide a unit, the deed can usually be amended without them. Either way, the approval file includes the co-owners’ consent for works on common parts, such as the facades or the load-bearing structure.
What happens to my share of the common charges?
In general practice your flat’s thousandths are divided between the two new flats, commonly in proportion to floor area, and the lift and heating tables are treated the same way, so the building’s total does not change. The amending deed records the new figures, and the building manager updates the monthly statement to show two flats.
How long is the approval for the works valid?
A small-scale works approval is valid for one year from issue. If the works are not finished in that time, it can be extended for one more year on the owner’s request, supported by the engineer’s reasoned report. Both periods are set by Article 329 of the Spatial Planning and Urban Planning Code.