Last reviewed: November 2026
When you’re renovating a flat, the easiest way to handle utilities during renovation in Greece is to keep your name on the electricity and water accounts. Let the trades use your meters, and only shut off what each job needs: specific circuits at the electrical panel, the flat’s own water valve, and the gas pipe, which a licensed installer should make safe when the cooker or boiler comes out. The key thing is to agree on who pays, take meter readings at the start and end of the project, and make sure you have all the right paperwork in order before you turn everything back on.
Key takeaways
- Keep the accounts in the owner’s name; the contractor uses your supply on terms agreed in writing.
- HEDNO’s supply removal (αποξήλωση παροχής) is for demolition or danger, not an ordinary refurbishment.
- A licensed gas installer should make the pipe safe when a cooker or boiler comes out, with changes recorded in the installation file.
- Shutting a building riser affects neighbours, so arrange it with the building manager.
- Photograph all three meters on day one and on handover day.
Should the electricity stay on while the trades work?
Yes, in almost every case: workers need power to use their tools and see what they’re doing. The electrician cuts the power to the circuits being worked on at the distribution board, and usually sets up a temporary board with protected sockets for everyone else to use.
You almost certainly don’t need to have the power supply removed (αποξήλωση παροχής ρεύματος). HEDNO (ΔΕΔΔΗΕ) describes taking away the cables, meter and box as a step for when a property is being demolished or the supply is dangerous, and only the owner can request it. If you’re renovating your kitchen or bathroom, or doing a full interior renovation, the meter stays where it is.
Who pays the bills during the works?
Keep the accounts in your name. Instead of handing them over to your contractor, write into the contract that the trades can use your supply and how their usage will be handled. Then take a reading at the start and end of the works to settle it.
What about rewiring or more power?
If you’re adding new circuits or need more power, like for an induction hob or heat pump, you may need a HEDNO supply increase and an installer’s certificate, known as ΥΔΕ. We’ve got all the details on this in our guide to rewiring a Greek apartment and the ΥΔΕ certificate.
What happens to the gas when the kitchen or boiler comes out?
In Attica, Enaon EDA is in charge of the gas network. Enaon is responsible for the supply up to your gas meter, and what happens after that is up to you. This means you’re responsible for the internal installation, the pipes and appliances inside your home. Enaon advises that maintenance and repairs go only to licensed technicians.
When you’re getting rid of an old cooker or boiler, make sure a licensed gas installer disconnects it and makes the open pipe safe. Don’t leave the job to the general builder. If you’re redoing your kitchen and need to move some pipes around, Enaon says existing installations may be changed only in line with the technical regulation. Keep a record of every change in the installation file, the folder holding the technical report and drawings.
If your kitchen or boiler is going to be out of action for a while, you can ask for the gas supply to be interrupted. The Enaon EDA ancillary services for interruption and reactivation help with this: Enaon can stop the supply if you ask, turn it back on when you’re ready, and check that the internal installation in your home is safe after it’s been disconnected.
A key thing to remember is that Enaon’s safety rules don’t allow you to change the ventilation openings in a way that cuts down on the air getting to a gas appliance area. False ceilings and enclosed balconies can block that air flow, so share your plans with the gas installer.
Water: the flat’s valve or the building riser?
EYDAP suggests that property owners should be aware of the location of the main and zone isolation valves and make sure they are working correctly. It’s a good idea to find and test the valve in your own flat before any work begins. For most jobs, closing it is enough.
If you need to replace a shared pipe or a valve that’s stuck open, you might have to shut the building riser, which cuts the water to other flats. Talk to the building manager (διαχειριστής) first, and give your neighbours notice by posting it in the entrance a day or two before, so they can make arrangements.
A few EYDAP rules are worth giving the contractor in writing:
- The owner is responsible for the internal plumbing, and EYDAP is not responsible for leaks in it.
- Nobody may interfere with EYDAP’s own installations, including the meter.
- The meter box must stay clear and accessible; rubble bags on top can lead to an estimated bill.
When you’re done with the replumbing work, turn off all the taps and look at your water meter. According to EYDAP, if the main valve is shut but the meter is still moving, there is a leak somewhere. If you notice a leak and want EYDAP to check the meter, you can apply online, at an EYDAP customer centre or at a KEP, as long as you’re the owner or have the owner’s written authorisation.
Reconnecting after rewiring or replumbing
- Electricity: HEDNO says any modified installation needs a new inspection by a licensed electrician; the rewiring guide above explains the ΥΔΕ and how to sign it from abroad.
- Gas: after a repair or adjustment, the authorised installer completes a re-inspection certificate for the internal pipework, or signs the maintenance logbook for a boiler room. Ask whether your changes also need an Enaon inspection, and who requests reactivation if the supply was interrupted.
- Water: ask the plumber to pressure test new pipes before tiling, and keep photos of the routes.
Keep everything in one folder, including the drawings. This way, if a defect appears later, you and the contractor can look at the same folder. Our post on how long a Greek contractor is responsible for defects explains why this matters.
A handover note on meter readings
At the start and end of the works, a simple one-page note keeps track of who used what. HEDNO lets you submit an electricity reading at any time by phone or online, with your 11-digit account number. You can even use the HEDNO online service request application to do it. Similarly, EYDAP and Enaon also let you register your readings online.
| Meter | What to record | Tip |
| Electricity | Reading without decimals; both K and M on a day and night meter | Check the supply number on the bill matches the meter plate |
| Water | Reading and meter number | Confirm which meter in the box is yours |
| Gas | Reading and meter number | Note whether the supply is on or interrupted |
Photograph each meter with the date visible and have the contractor sign the note.
“On the first morning of any renovation, photograph all three meters and the flat’s water valve, and send the photos to the owner and the contractor together. Do the same at handover. It takes ten minutes, and nobody ever has to argue about a water bill or wonder whether the gas was left safe.”
Yanis Zisis, Founder, Home Watch Athens
Managing it all from abroad
When you’re getting ready to renovate, you’ll need someone to keep an eye on things at the site. That’s where our renovation management service in Athens comes in: we handle the coordination with your contractors. As part of membership, we also visit your home once a month and send you an update with photos. Before the work even starts, it’s a good idea to double-check your insurance cover for damage to neighbours during a renovation. You should also figure out if you’ll need an engineer to oversee the renovation.
This is just general information, so don’t take it as technical or legal advice. For your installation, it’s best to hire a licensed installer.
If you’re getting ready to renovate and need someone local in Athens, Apply for Membership.
Frequently asked questions
Do I need to ask HEDNO to disconnect the electricity before a renovation?
Usually not. Your electrician isolates the circuits being worked on at the distribution board and keeps a safe supply for the trades. HEDNO’s supply removal procedure, αποξήλωση παροχής, covers taking away the cables, meter and box when a property is demolished or the supply is dangerous. For a normal flat renovation, the meter and account stay as they are.
Should the contractor put the electricity bill in their name?
We recommend keeping the accounts in the owner’s name throughout. Changing the holder for a few months only adds paperwork. Instead, agree in writing that the trades may use your supply and how usage is handled, and record the meter readings at the start and at handover.
What happens to the gas supply when the kitchen is removed?
A licensed gas installer should disconnect the cooker or boiler and make the pipe safe. Enaon EDA is responsible for the supply up to the gas meter, and the internal installation is the owner’s. Changes to the pipework must follow the technical regulation and be recorded in the installation file. For longer works, the supply can be interrupted and later reactivated.
Can I shut off the whole building’s water for my renovation?
Only by arrangement. Shutting the building riser cuts water to other flats, so agree a time with the building manager and give neighbours notice a day or two ahead. For most jobs, closing your own flat’s isolation valve is enough, and EYDAP advises owners to check that their valves open and close properly.
Why record the meter readings at the start and end of the works?
Readings taken on the first day and at handover show how much electricity, water and gas the works used, which settles whatever you agreed with the contractor about usage. Photograph each meter with the date visible and have the contractor sign the note. HEDNO, EYDAP and Enaon all let you register a reading online.