Last reviewed: November 2026
When owners manage renovation permits from abroad Greece-wide, most follow a similar process. The engineer takes care of submitting the application online, and then the owner reviews and confirms a few details digitally. After that, someone local takes over and deals with the rest of the paperwork. As the owner, your role is limited to providing a few essential documents, such as appointing the engineer, proving you own the property, and, if the renovation affects shared areas of the building, the consent of your co-owners. Everything else can be taken care of by your engineer or someone you’ve authorised to act on your behalf through the gov.gr platform.
Key takeaways
- Your engineer files the approval on e-Adeies, but in your name.
- You are the “employer” for the works with EFKA, registered before work starts.
- A gov.gr authorisation lets someone act for you on defined tasks.
- Sort out your AFM, TAXISnet codes and a registered mobile first.
- Keep a closing file: approvals, certificates, EFKA papers and invoices.
Who signs what during a renovation in Athens?
Your engineer will let you know what you need to do for your project. If you’re just making some internal changes, you will usually need far less than a full permit.
| Step | Who signs or files | How you do it from abroad |
| Appointing the engineer (study and supervision) | Owner appoints; engineer accepts | Signed declaration; ask the engineer which form they need |
| Ownership documents (title deed, cadastral sheet) | Owner provides | Send copies or authorise someone |
| Building permit or small-scale works approval (e-Adeies) | Engineer files, in the owner’s name | Review the file |
| Consent for shared parts (facade, roof, structure) | Co-owners of the building | General assembly minutes or signed declarations, often arranged via the building manager |
| EFKA registration of the works | Owner, or a legally authorised person | Online with TAXISnet, or a representative |
| Skip, scaffolding and pavement permits | Contractor, engineer or owner | Agree in writing who applies |
| Electrical installation and HEDNO paperwork | Electrician; owner signs supporting papers | Sign scans or authorise someone |
| Invoices and payments | Contractor issues; owner pays | Bank transfer, invoices in your name |
If you’re not sure what some of the job titles on your paperwork mean, we have a guide that explains the Greek words on your renovation quote and permits.
What does the engineer file on your behalf?
In Greece, permits go in online using a platform called e-Adeies, which is run by the Technical Chamber of Greece, or TEE for short. To do this, engineers use their own special TEE codes to log in and submit the paperwork, so it’s their responsibility. For smaller apartment renovations, like changing the layout inside or doing some work on the facade or roof with scaffolding, you’ll need a document called a small-scale works approval (Έγκριση Εργασιών Δόμησης Μικρής Κλίμακας). This type of approval is used for jobs that don’t affect the main (load-bearing) structure of the building. If you’re planning something bigger, you’ll need to get a full building permit.
The owner’s name is on the application, but it’s the engineer who submits it and is responsible for the submission. A small-scale works approval is valid for one year, and can be extended once, for another year, if the owner asks and the engineer gives a justification. All the necessary documents are listed in the official procedure for small-scale building works approval.
What the engineer cannot do without you
- Appoint themselves: your written appointment is part of the file.
- Prove ownership: the title deed, cadastral extract or similar comes from you.
- Consent for shared parts: facade, roof or structural work needs the co-owners’ consent.
- Log into your accounts: your TAXISnet codes are personal, so use an authorisation instead.
Gov.gr authorisation or power of attorney: which one do you need?
For most day-to-day renovation tasks, you usually just need a gov.gr authorisation (εξουσιοδότηση) to get things done. This is something you can issue yourself, along with solemn declarations (υπεύθυνες δηλώσεις), using the gov.gr Digital Documents platform. The key thing to remember is that the authorisation only covers exactly what you’ve written in it, so be specific. For example, you might say something like “to submit and collect documents for the renovation of my apartment at [address]”. Our separate guide explains how gov.gr authorisations and e-solemn declarations work from abroad.
Some things can’t be done with an online authorisation, typically anything involving a notary or a change to ownership rights. In those cases, you need a notarial power of attorney, which Greek consulates handle by appointment.
Which credentials do you need from abroad?
Before work starts, check you have three things:
- An AFM (Greek tax number). Everything else sits on it.
- TAXISnet codes. These log you into gov.gr and EFKA. Check they work.
- A mobile number registered on the National Communications Registry (EMEp). Gov.gr sends confirmation codes here, and a foreign mobile is accepted.
If you own a home with a brother or sister, or with someone else, you’ll each need your own codes. This is because you might each have to confirm things separately.
Registering the works with EFKA
As the owner, you’re the “employer” of the workers, and you need to get the EFKA registration sorted out before they start on site. You can do this online yourself or have someone do it for you, as long as you’ve legally authorised them to act on your behalf.
Paperwork around the building site
When you’re renovating, it affects the street and the building too. You might need permits from your municipality for skips, scaffolding and rubble removal. We cover those in our post on municipal permits for skips, scaffolding and rubble in Athens. Make sure you and your contractor decide who’s going to handle getting those permits in your contract.
Where electrical work that requires paperwork for HEDNO, a licensed electrician will sign and stamp a form called the installer’s declaration, or ΥΔΕ. The owner or account holder signs the accompanying documents. For gas work, you’ll work with a licensed gas installer who will let you know what you need to sign as the owner.
Let the building manager (διαχειριστής) know before you begin; things like noise hours and using the lift are their concern.
“Sort out your codes before you sign with an engineer. The most common delay I see is not the permit itself, it is an owner abroad who cannot log in to confirm one small step. Test your TAXISnet login, make sure your mobile is registered, and agree from day one who in Athens is allowed to act for you, and on what.”
Yanis Zisis, Founder, Home Watch Athens
What should be in your closing file?
When the work is done, collect one folder, digital or paper, with:
- The building permit or small-scale works approval, with its number.
- The engineer’s appointment and any supervision declarations.
- The EFKA registration and proof that contributions are settled. EFKA’s insurance clearance for construction works is asked for if ownership later changes, for example by gift.
- Electrical and gas certificates from the licensed installers.
- Co-owners’ consent, if shared parts were touched.
- Every invoice, in your name, with proof of payment.
If things come to a halt before you get to this stage, see our guide on what to do if your renovation contractor stops turning up.
Having someone in Athens for the paperwork
You still need someone to pick up papers, meet with the engineer at the site, and make sure everything is being built as planned. That’s where we come in: our renovation oversight service in Athens takes care of all that for our members, plus we do a monthly home visit and send you a photo update. We quote each renovation project separately. If you would like us to be your person in Athens, Apply for Membership.
Frequently asked questions
Can someone manage residential permits for a renovation in Greece on my behalf?
Yes. Your engineer files the permit or small-scale works approval on the e-Adeies system, in your name, using their own professional codes. For the remaining steps, such as collecting documents or registering the works with EFKA, you can authorise a person through gov.gr. You still give the owner’s consents yourself, usually digitally, so you rarely need to travel to Athens.
Do I need a power of attorney to renovate my Athens apartment from abroad?
Usually not. A gov.gr authorisation, signed online with your TAXISnet codes and a registered mobile, covers most renovation tasks and is legally equivalent to an authorisation with a certified signature. A notarial power of attorney is generally needed only for acts involving a notary or ownership rights. Ask your engineer early, as consulates handle powers of attorney by appointment.
How long is a small-scale works approval valid in Greece?
A small-scale works approval (Έγκριση Εργασιών Δόμησης Μικρής Κλίμακας) is valid for one year. If the works are not finished in time, the owner can ask for one further year, supported by a justification from the engineer. Plan the schedule with your engineer and contractor at the start, so the approval does not run out while you are abroad and the job is only half done.
Which renovation documents should I keep after the work is finished?
Keep the permit or small-scale works approval, the engineer’s appointment, the EFKA registration and proof that contributions are settled, the electrical and gas certificates, any co-owners’ consent, all invoices with proof of payment, and before and after photos. Store them together, digitally if possible, because they may be asked for if ownership of the property changes later.