To renovate an inherited apartment in Athens while you live abroad, start by checking with your lawyer that the heirs can act. Then record what the apartment looks like now, decide what to do with the belongings, and agree as a family on budget, scope and who makes the final calls. Give one trusted person written authority over access, and agree the scope with your contractor in writing before anything starts.
Key takeaways
- Ask your lawyer before any works: for deaths before 16 September 2026, handling estate property can count as accepting the inheritance.
- Record the apartment room by room before anything moves, so the family and contractors start from the same picture.
- Agree in writing what the renovation is for, who pays which share and who makes day-to-day decisions.
- Give one trusted person the keys and written authority, and tell the building manager before works begin.
- Fix the scope, approvals and budget on paper; works start from €600/m² (excluding 24% Greek Tax), and quotes often rise.
Can you renovate an inherited apartment in Athens before the inheritance is settled?
This is a question for your lawyer, not your contractor, because a renovation is a decision about estate property.
For deaths before 16 September 2026, an heir can accept an inheritance through their actions, without signing any papers. AADE guidance says that when an heir manages or disposes of inherited property, those acts must be examined to see whether they show an intention to keep the inheritance. Once accepted, it can’t be renounced. Law 5303/2026 changed Greek succession law for deaths on or after 16 September 2026, with transitional rules for some earlier cases. Our first-year guide for heirs who live abroad covers the deadlines, tax and the new law.
There’s a practical aspect too. When an engineer files the approval for works, they need the owner’s or legal right holder’s details and a cadastral document for the property. If the acceptance and registration with the Cadastre haven’t been completed yet, your lawyer can advise whether to wait. An emergency like a burst pipe is different: under the Greek Civil Code, any co-owner can take the measures needed to protect a shared property when danger is imminent. A full renovation is not one of those.
How do you record the apartment’s condition before works?
Before you ask for quotes, take a close look at the apartment itself, not just the things inside. Go through each room, or ask someone you trust to do it, and take pictures of:
- walls and ceilings, especially behind wardrobes on outside walls, where damp often hides
- the electric panel, sockets and any old cloth-covered wiring
- taps, pipes under sinks, the water heater and any signs of past leaks
- windows, shutters, balcony doors and balcony drains
- floors, original doors and anything the family may want to keep, such as marble, mosaic or wooden parquet
Gather the documents that affect the works: the building permit and plans, any regularisation papers, the building regulation (kanonismos) and the latest koinoxrista statements. In older Athens apartments it’s not uncommon to find enclosed balconies or moved walls that don’t match the plans, so your engineer should check this before designing anything new.
Share your photos and list with every heir, so contractors quote on the same details and nobody argues later about what was already there.
What happens to the belongings before works begin?
Most renovations need an empty apartment, or at least empty rooms. Clearing a family home has its own steps: take photographs first, find the important papers, ask your lawyer before anything leaves, and decide together as a family what to keep. We explain these steps in our guide to clearing an inherited family home in Athens.
For the renovation itself, two things matter. First, mark everything that stays in place during the works, like a built-in cabinet or the old marble sink your family wants restored, and tell the contractor in writing. Second, get valuables, documents and photographs out before the workers arrive.
How do co-heirs agree on renovating the family apartment?
Renovating a family apartment in Greece usually means several heirs living in different countries. Under the Civil Code, management of a shared property belongs to all co-owners together, and each co-owner bears shared costs in proportion to their share. In practice, families do best when they put a few things in writing before the first quote:
- What the renovation is for. Family use, a long-term second home or simply putting right years of wear. This decides the level of finish.
- The budget ceiling, and who pays which share and when.
- What must be kept, such as original floors, doors or fittings.
- One decision-maker for day-to-day questions, and a limit above which every heir must approve a change.
Put this in a short family agreement, or even an email that everyone replies to. If the heirs can’t agree on the basics, pause the renovation; a half-finished apartment is much harder to resolve than an untouched one.
Who can give contractors access to the apartment, and on what authority?
Keys to an inherited home are often scattered among neighbours, relatives and an old cleaner. Collect every set you can find, change the lock if anyone is unsure who has a key, and give the keys to one person you trust.
That person needs written authority from the heirs. For simple matters, such as letting a contractor in or dealing with the building manager, a written authorisation is often enough. Heirs with Taxisnet or Greek web banking codes can issue one through gov.gr’s online authorisation service. For signing contracts, dealing with authorities or handling the inheritance itself, your lawyer may advise a formal power of attorney. Our guide on whether you need a power of attorney for property issues in Greece explains the difference.
Let the building manager (diaxeiristis) know before any work starts. The kanonismos may set rules on working hours, using the lift, skips and deliveries.
How do you agree the scope of works from abroad?
Greek diaspora apartment renovations go wrong when the plan only exists in phone calls, whoever manages the works. Agree a written scope that lists every room, task and material, with what’s included and what’s not. In older Athens apartments, the priorities are usually the electrics, plumbing, windows, bathrooms and kitchen, because these are the hardest to change later.
Check the approvals you need early. Internal changes that don’t affect the load-bearing structure can fall under the small-scale building works approval, filed online by an engineer and valid for one year. Works costing more than €25,000 per property generally need a full building permit, and changes to common parts of the building, like the façade or roof, need the co-owners’ consent. Our guide on whether you need a permit to renovate an apartment in Greece goes into more detail.
On budget, works start from €600/m² (excluding 24% Greek Tax). The final cost depends on the scope and the finishes you choose. Contractor quotes in Greece often end up higher than first quoted, so build in a contingency, ask for an itemised breakdown and agree in writing how changes are priced and approved.
“Before anyone talks about tiles or kitchens, get three things on one page: what your lawyer says you can do, what the family has agreed, and who holds the keys. With inherited homes, the renovation itself is rarely the hard part. The hard part is a scope that changes every time a different relative visits, so agree it once, in writing, and let one person run it.”
– Yanis Zisis, Founder of Home Watch Athens
How do you keep the whole family informed during the works?
Create one shared folder for the baseline photos, family agreement, scope, quotes, invoices and approvals. Ask for dated photo updates at each stage, and keep a simple log of what changed, who approved it and what it cost. Pay for each stage by traceable bank transfer, and check the work before releasing the next payment. At handover, make a snagging list and collect the warranties, the electrician’s certificate and the engineer’s paperwork.
How Home Watch Athens can help
When your family is spread across countries, one trusted person on the ground is a real help. With our renovation oversight in Athens, Yanis can hold the keys, meet contractors before they quote, check the work against the agreed scope and send every heir photo reports on WhatsApp. We also carry out renovations ourselves, and once the works are done, our monthly Home Watch visit looks after the apartment while it’s empty. We are here to guide you, not to profit from you. Apply for Membership and Yanis will reply within 24 hours.
Frequently asked questions
Can I start renovating before the inheritance is accepted?
Ask your lawyer first. For deaths before 16 September 2026, acts of management or disposal of estate property can count as tacitly accepting the inheritance, which rules out renouncing it later. Deaths from that date fall under Law 5303/2026. The engineer filing any approval also needs the owner’s details and a cadastral document, so the paperwork usually has to come first.
Do all co-heirs have to agree to the renovation?
Management of a shared property belongs to all co-owners together, and each pays shared costs in proportion to their share. In practice, a renovation runs far more smoothly with every heir on board. One co-owner acting alone can only take urgent measures to protect the property. Your lawyer can confirm which decisions need everyone’s agreement in your family’s situation.
Who should hold the keys during the works?
One trusted person, with written authority from the heirs. Collect every existing set first, change the lock if you are unsure who has copies, and tell the building manager who is responsible. Contractors should collect and return keys through that person, so there is always a clear record of who entered the apartment and when.
Does an inherited apartment need a permit to renovate?
It depends on the works, not the inheritance. Internal changes that don’t affect the structure often fall under the small-scale works approval, filed by an engineer and valid for one year. Larger budgets or works on common parts need more. Older apartments may also have past changes that don’t match the plans, which your engineer should check first.
How much does it cost to renovate an inherited apartment in Athens?
Works start from €600/m² (excluding 24% Greek Tax). The final figure depends on the apartment’s condition, the scope and the finishes chosen. Inherited homes often hide old wiring, pipes or damp that only appear once work starts, and contractor quotes in Greece often end up higher than first quoted, so keep a contingency.
This guide is general information, not legal or tax advice. Inheritance, title and tax questions depend on the date of death, any will and your co-heirs. For your own situation, you can always consult a Greek lawyer or accountant.
Last updated: November 2026