Converting a shop, office or storage area into a living space is a change of use in Greece (αλλαγή χρήσης), which involves a planning process: it is not just about renovating the place. To make this happen, an engineer has to submit the file electronically, and it will normally only get approved if two main conditions are met: the area’s planning rules allow for a home at that specific address, and the space itself is suitable for people to live in. The rules are outlined in Article 199 of Law 5306/2026, which is the Spatial Planning and Urban Planning Code. Typically, shops and offices have a route to approval, but basement storage rooms often don’t.
Key takeaways
- Shops and offices are main-use spaces, so converting them is mostly a question of land use and of the building’s own rules. Storage rooms and basements are auxiliary spaces and rarely qualify.
- Depending on what the conversion touches, the engineer needs a building permit, a small-scale works approval, or only an update of the Building Identity.
- The building’s regulation can restrict the use of a unit, whatever planning law allows.
- After approval, the E9, the Building Identity and the utility accounts all have to show a home.
What does the law say about change of use?
The rules are laid out in Article 199 of the Code, which says that you can’t change how a building, or part of one, is used unless the new use is provided for by the planning rules that apply to the property. It breaks this down into two different situations.
When a building gets a new use, it can really change things. The new use can alter the figures on the building’s coverage diagram, adding more design load to the structure or needing new pathways for services like plumbing or electricity through other floors or shared spaces. To make these changes happen, the engineer needs to get a building permit. After that, the Electronic Building Identity needs to be updated to reflect the new use.
The second situation is a space that already has a building permit for a specific use, where the new use is allowed in the area. If none of those effects come up, you don’t need a building permit: the Building Identity is simply updated. If you’re doing some building work, there are still rules to follow. Where you’re rearranging the inside or carrying out change-of-use works that need no permit under Article 199, and you’re not touching the load-bearing structure, Article 315 of the Code puts the job under the small-scale works approval. The file then includes the engineer’s sworn declaration that the structure is left alone. We have a guide that explains the three renovation permit routes in Greece and what each approval involves.
According to paragraph 4 of the same article, if someone wants to change how a building is used, they also need to make sure people with disabilities can move around the shared spaces, as long as the load-bearing structure of the building isn’t altered.
What changed in July 2026?
In July 2026, Parliament voted to update Article 199, so that existing buildings can be turned into homes. If a building sits inside an approved town plan or settlement, the article now lets its use change to a home by way of exception, whatever land uses are in force for the area. There is a condition for buildings that were put up with a deviation from the planning rules: that deviation had to be granted by 31 December 2025. To make this happen, you need a building permit, and the Central Council of Architecture has to give a favourable opinion before it is issued. We’ve got more in our post on what the 2026 planning code means when you renovate.
Which spaces can become a home?
Greek planning law sorts spaces into two groups.
| Type of space | Examples | What a conversion to a home involves |
|---|---|---|
| Main use (κύρια χρήση) | A shop, an office, a workshop on the ground floor | Already counted as main use. What remains is the land use of the area, the building’s own rules and the standards for a dwelling. |
| Auxiliary use (βοηθητική χρήση) | A storage room, a basement, a parking space, a plant room | Approved to serve the building, not to be lived in. Making it main use adds floor area that the plot must still have available, and the room must meet every standard for a dwelling. |
A semi-basement can land in either group. If the building permit says it’s a shop or office, then it’s main-use space and follows the first row of the table. But if it’s listed as storage, then it falls under the second. What really matters is what’s on the approved plans and the building permit, not what’s written on the door. We’ve got a separate post that talks about renovating a basement storage room for storage.
What must the space itself have?
A home needs to follow the rules set by the Building Code (Κτιριοδομικός Κανονισμός) for main-use rooms.
- Ceiling height. Article 7 of the Code sets the free height that rooms must have. Basements and storage rooms often fall short.
- Natural light and ventilation. The rooms people live in need daylight and fresh air, which is where windowless basement rooms fail.
- Parking. The engineer checks the building’s parking obligation against the new use as part of the file.
What does the building have to say about it?
The other half is private. This includes the building’s regulation, known as κανονισμός πολυκατοικίας, and the deed of horizontal ownership, or σύσταση οριζόντιας ιδιοκτησίας. Both of these are notarial deeds that every owner has to follow, and they are drawn up by a notary.
Each unit is described in the deed. Then there’s the regulation, which may say how the units can be used. For example, some buildings have a regulation that says the ground floor has to be used for commercial purposes, while others don’t allow any change to how a unit is used. If the regulation gets in the way of the new use, it needs to be changed first. To do that, a new notarial deed has to be signed by the co-owners.
When work goes past your own walls, the neighbours get involved too. If you need to put in a new drain pipe that goes through the basement, or change the front of the shop, it affects parts of the building that everyone shares. Then, to get approval, the other owners’ consent documents are added to the file.
What paperwork follows the approval?
Other records still show a shop until someone updates them.
- Building Identity. The engineer updates the Electronic Building Identity through the Building Identity registry on gov.gr. The permit or approval itself is issued through the e-Adeies system of the Technical Chamber.
- E9. The property declaration at the tax authority holds the descriptive details of each property, and it is filed again whenever those details change. The new description goes on an amended E9 declaration at AADE.
- Cadastre. Where the conversion needed an amendment to the deed of horizontal ownership or to the regulation, the amending notarial deed is submitted to the Cadastre as a registrable deed.
- Utilities. The electricity supplier and the water company are given the new documents, so that the accounts are held for a home and not for a shop.
If someone is already living in a space without approval, that’s a different story, and we talk about it in our guide to unauthorised changes in a Greek property, which covers spaces used without permission.
What does the renovation add?
A shop is usually a big open space with a small toilet. If you want to live there, it needs more: a proper bathroom, a kitchen to cook in, hot water, and a way to keep warm.
Drainage is a big deal and needs a lot of attention. For ground-floor units, there’s often only one connection for waste, and if you want to change the route through the common areas, that is the kind of change Article 199 sends to a building permit. Insulation is also important: a shopfront is basically a big glass wall on the pavement, and the floor is often right on the ground. If you replace the shopfront with a wall and windows, it changes the facade, so that’s something that goes in the approval file.
A common family case: the shop under the family flat
Lots of families who live in other countries inherit a flat on the first floor and a small shop below it that hasn’t been used in years. The plan is to turn the ground floor into a home for a parent who can’t manage stairs any more.
First comes the paperwork. The engineer starts by collecting the building permit and the plans that have been approved. They then read through the regulation and the deed. They also confirm the land use for that street and measure the space. Only after that are the drawings made and the application submitted.
“When I open a closed family shop for the first time, I look at three things before anyone talks about kitchens: how high the ceiling is, where daylight actually reaches, and where the waste pipe leaves the unit. Then I ask the family for the building’s regulation. Those four answers tell you early whether this can be a home, before a single drawing is made.”
Yanis Zisis, Founder, Home Watch Athens
How we help members with a conversion
If you live abroad and you’re a member, we open the space for the engineer and keep an eye on the works on site for you. That happens through our renovation oversight service in Athens, which is quoted separately from membership. Every month, Yanis still visits your home and sends a photo update, right through the works. If you own a home in Athens or Attica and live abroad, you can Apply for Membership.
Frequently asked questions
Can I convert a shop to an apartment in Greece?
Yes, where the planning rules for the area accept residential use and the space meets the standards for a dwelling. An engineer files the change of use from shop to residence, which needs a building permit, a small-scale works approval or only a Building Identity update, depending on its effect on the building.
Can a storage room become an apartment in Greece?
Rarely. A storage room is an auxiliary space, approved to serve an apartment and not to be lived in. Converting it means adding main-use floor area, which the plot must still have available, and the room must meet the height, daylight and ventilation standards for a home.
Is a semi-basement change of use possible?
It depends on what the building permit says the semi-basement is. If it was approved as a shop or an office, it is main-use space and can follow the same route as any shop, provided the ceiling height, daylight and ventilation are enough for a dwelling. If it was approved as storage, it faces the same obstacles as a storage room.
Do the other owners in the building have to agree?
Their agreement is needed in two situations. The first is when the building’s regulation or the deed of horizontal ownership restricts the use of the unit, because amending either takes a new notarial deed signed by the co-owners. The second is when the works affect common parts, such as the facade or pipes through shared areas.